← Back to the full dossier
StrataAuditor Public-record dossier

4-8 Madeira Street Sylvania

SP 49833 Sylvania Sutherland Shire New South Wales

Verdict

Public record: 4 tribunal matters, no building-work orders. A reasonable pre-screen, but not the full picture, the financials and minutes that decide the purchase are in the report, not the registers. Read it, and obtain a section 184 strata search, before you bid.

Cost exposure

Indicative, itemised estimate of what one average lot here could face, built only from this scheme's public-record signals. Indicative ranges, not this building's actual figures, and not financial advice.

Moderate
Good case $600 per lot
Expected $5,000 per lot
Worst case $18,900 per lot
  • Tribunal and legal costs

    Indicative per-lot share of tribunal and legal costs in a strata dispute (NCAT). Scaled for: 4 matters.

    $5,000

Litigation · 4 matters

  • Georgeski v Owners Corporation SP49833 [2005] NSWSC 311

    Costs and procedure NSWSC 11 April 2005

    PROCEDURE - costs - where defendant files submitting appearance after claims in summons amended - whether defendant's costs

  • Georgeski v Owners Corporation SP49833 - Costs [2005] NSWSC 28

    Costs and procedure NSWSC 4 February 2005

    PROCEDURE - costs - no question of principle

  • Georgeski v Owners Corporation SP49833 [2004] NSWSC 1096

    Other NSWSC 22 November 2004

    REAL PROPERTY - Crown lands - licence granted by Crown over site of jetty and slipway on bank of tidal river - nature of rights created - whether jetty and slipway are fixtures - effect of provisions of licence declaring them to be "property of" licensee but precluding alteration, removal and destruction while licence subsists - common law rights of public in relation to tidal foreshore - attenuation thereof by statute - TORTS - trespass to land - whether contractual licensee without right of ex

  • Georgeski v Owners Corporation SP49833 [2004] NSWSC 945

    Other NSWSC 7 October 2004

    EVIDENCE - admissibility - correspondence on settlement negotiations - prima facie inadmissible - whether admissible because of need to "control the conduct of a proceeding" or under exception for "deliberate abuse of power"

Decisions naming this scheme, from NSW Caselaw (NCAT and the courts). The quoted line beneath each is the decision's own catchwords; the topic tag is our grouping of those words. Whether a matter helped or hurt the scheme is not assessed here.

Statutory-warranty outlook

Structural cover
Likely expired · est. expiry 13 June 2002
Non-structural cover
Ran to 13 June 2002

A single 7-year warranty period applies because the scheme was registered before the 1 February 2012 reform. Estimated from the registration date, not the completion date or building contract, so treat the dates as indicative.

Evidence ledger

Registry-backed record: matched to a scheme on the register by its plan number.

Evidence ledger: what was checked, what it found, how strong the match, and when it was last checked.
CheckedFoundMatchLast checked
Registry and parcelNSW Strata Hub, with geometryDirectAwaiting first run
Governance: AGM, managing agent, annual reportingNot yet checkedNot matchedNot harvested here yet
Litigation: NCAT and courts4 mattersDirect28 June 2026
Levies and financialsNot yet checkedNot matchedNot in the public record
Defects and building-work ordersChecked, none foundDirect28 June 2026
Fund balances, current levies, minutes, defects not yet litigatedNot on the public recordNot matchedNever in the public record

What was checked, what it found, how strong the match, and when each source last ran. A source that has not run here yet reads as not checked, never as checked and clear.

Compiled by StrataAuditor from NSW Strata Hub (DCS Spatial Services) and the relevant licence registers. Litigation from NSW Caselaw (NCAT and the courts). Records only, as published; unknowns are shown as unknowns.

Coverage caveat: this reflects only what is on the public record for New South Wales at the time of generation. An empty matters or orders count is not a clean bill: fund balances, current levies, minutes, and defects not yet litigated are never on the public record. Obtain the strata report before you bid.

Public-record summary, not legal or financial advice.

Generated 4 July 2026 · StrataAuditor

strataauditor.com/building/nsw:SP49833