60 Duffy Avenue Thornleigh
SP 68372 Thornleigh Hornsby New South Wales
Verdict
Public record: 6 tribunal matters, no building-work orders. A reasonable pre-screen, but not the full picture, the financials and minutes that decide the purchase are in the report, not the registers. Read it, and obtain a section 184 strata search, before you bid.
Cost exposure
Indicative, itemised estimate of what one average lot here could face, built only from this scheme's public-record signals. Indicative ranges, not this building's actual figures, and not financial advice.
Elevated- $27,700
Serious building-defect rectification
Indicative per-lot serious-defect rectification levies (NSW Serious Defects in Residential Apartments research report, 2021; strata special-levy reporting). Scaled for: 1 matter.
- $6,300
Tribunal and legal costs
Indicative per-lot share of tribunal and legal costs in a strata dispute (NCAT). Scaled for: 6 matters.
Litigation · 6 matters
The Owners – Strata Plan No 68372 v Allianz Australia Insurance Limited (No 2) [2015] NSWSC 729
Costs and procedure NSWSC 12 June 2015
PRACTICE AND PROCEDURE – Costs – Departing from the general rule – Late joinder of a defendant – Plaintiff’s delay in conduct of proceedings – Claims that failed or were abandoned – Expert reports prepared but not relied on – Costs as between the defendants PRACTICE AND PROCEDURE – Costs – Interest on costs – Where plaintiff guilty of unexplained delays – Whether reasons for delay are relevant to question of whether interest on costs should be awarded
The Owners - Strata Plan No 68372 v Allianz Australia Insurance Limited [2014] NSWSC 1807
Building defects NSWSC 18 December 2014
BUILDING AND CONSTRUCTION - adoption of referee's report - UCPR, r 20.24 - application of parties opposing adoption of referee's report on certain matters - whether third defendant developer a "developer" under Home Building Act 1989 (NSW), s 3A and thus liable to plaintiff owners corporation under s 18C for contractor's breach of s 18B implied warranties - whether claim brought under s 18C an apportionable claim - whether referee erred in selecting cheaper option for rectification of laundry wa
Owners Strata Plan No 68372 v Allianz Australia Insurance Ltd [2014] NSWSC 223
Other NSWSC 12 March 2014
PROCEDURE - Subpoenas - Application to set aside - Waiver of legal professional privilege - Was privilege waived by failure of counsel to object to questions in cross-examination?
The Owners - Strata Plan No 68372 v Allianz Australia Insurance Limited [2013] NSWSC 2009
Other NSWSC 19 December 2013
PRACTICE & PROCEDURE - application to amend Scott Schedule - whether statute barred
The Owners - Strata Plan No. 68372 v Allianz Australia Insurance Limited [2013] NSWSC 1095
Costs and procedure NSWSC 6 August 2013
PRACTICE AND PROCEDURE - amendments to defence and cross-claim - whether application to amend made too late and would cause undue prejudice
Strata Plan 68372 v Allianz [2012] NSWSC 691
Other NSWSC 18 June 2012
[PROCEDURE] - civil - parties - joinder - whether joinder of the fourth defendant should be set aside - whether joinder is vexatious or embarrassing where limitation defence available. [LIMITATION OF ACTIONS] - limitation defence - whether plaintiff's cause of action is statue barred.
Decisions naming this scheme, from NSW Caselaw (NCAT and the courts). The quoted line beneath each is the decision's own catchwords; the topic tag is our grouping of those words. Whether a matter helped or hurt the scheme is not assessed here.
Statutory-warranty outlook
- Structural cover
- Likely expired · est. expiry 12 August 2010
- Non-structural cover
- Ran to 12 August 2010
A single 7-year warranty period applies because the scheme was registered before the 1 February 2012 reform. Estimated from the registration date, not the completion date or building contract, so treat the dates as indicative.
Evidence ledger
Registry-backed record: matched to a scheme on the register by its plan number.
| Checked | Found | Match | Last checked |
|---|---|---|---|
| Registry and parcel | NSW Strata Hub, with geometry | Direct | 16 August 2026 |
| Governance: AGM, managing agent, annual reporting | Not yet checked | Not matched | Not harvested here yet |
| Litigation: NCAT and courts | 6 matters | Direct | Awaiting first run |
| Levies and financials | Not yet checked | Not matched | Not in the public record |
| Defects and building-work orders | Checked, none found | Direct | 16 August 2026 |
| Fund balances, current levies, minutes, defects not yet litigated | Not on the public record | Not matched | Never in the public record |
What was checked, what it found, how strong the match, and when each source last ran. A source that has not run here yet reads as not checked, never as checked and clear.