51-59 Wheelers Lane Dubbo
SP 72250 Dubbo Dubbo Regional New South Wales
Verdict
Public record: 3 tribunal matters, no building-work orders. A reasonable pre-screen, but not the full picture, the financials and minutes that decide the purchase are in the report, not the registers. Read it, and obtain a section 184 strata search, before you bid.
Cost exposure
Indicative, itemised estimate of what one average lot here could face, built only from this scheme's public-record signals. Indicative ranges, not this building's actual figures, and not financial advice.
Low- $4,300
Tribunal and legal costs
Indicative per-lot share of tribunal and legal costs in a strata dispute (NCAT). Scaled for: 3 matters.
Litigation · 3 matters
The Owners – Strata Plan No 72250 v Nugent (No2) [2025] NSWCATAP 227
Costs and procedure NSWCATAP 12 September 2025
COSTS – general rule that costs follow the event – proceedings dismissed – no exception to the general rule established
The Owners – Strata Plan No 72250 v Nugent [2025] NSWCATAP 183
Costs and procedure NSWCATAP 5 August 2025
APPEAL – whether reasons were inconsistent with orders-whether decision was not fair and equitable or against the weight of evidence- no basis to grant leave.
The Owners Strata Plan No. 72250 v Letmin Pty Limited t/as Dubbo Powder Coating [2020] NSWDC 378
Repairs and common property NSWDC 16 July 2020
TORTS– Negligence – Nuisance – Where Plaintiff Owners Corporation of Strata Plan claims First and Second Defendant caused damage to common property – Where First Defendant runs powder coating business out of Second Defendant’s Lot in Strata Complex – Whether garnet and powder was emitted during course of First Defendant’s business – Whether duty is owed by the Second Defendant to Plaintiff – Failure to take proper precautions in running of business – Whether the First Defendant’s business consti
Decisions naming this scheme, from NSW Caselaw (NCAT and the courts). The quoted line beneath each is the decision's own catchwords; the topic tag is our grouping of those words. Whether a matter helped or hurt the scheme is not assessed here.
Statutory-warranty outlook
- Structural cover
- Likely expired · est. expiry 5 April 2011
- Non-structural cover
- Ran to 5 April 2011
A single 7-year warranty period applies because the scheme was registered before the 1 February 2012 reform. Estimated from the registration date, not the completion date or building contract, so treat the dates as indicative.
Evidence ledger
Registry-backed record: matched to a scheme on the register by its plan number.
| Checked | Found | Match | Last checked |
|---|---|---|---|
| Registry and parcel | NSW Strata Hub, with geometry | Direct | Awaiting first run |
| Governance: AGM, managing agent, annual reporting | Not yet checked | Not matched | Not harvested here yet |
| Litigation: NCAT and courts | 3 matters | Direct | 28 June 2026 |
| Levies and financials | Not yet checked | Not matched | Not in the public record |
| Defects and building-work orders | Checked, none found | Direct | 28 June 2026 |
| Fund balances, current levies, minutes, defects not yet litigated | Not on the public record | Not matched | Never in the public record |
What was checked, what it found, how strong the match, and when each source last ran. A source that has not run here yet reads as not checked, never as checked and clear.