84 Epsom Road Zetland
SP 95242 Zetland Sydney New South Wales
Verdict
Public record: 2 tribunal matters, no building-work orders. A reasonable pre-screen, but not the full picture, the financials and minutes that decide the purchase are in the report, not the registers. Read it, and obtain a section 184 strata search, before you bid.
Cost exposure
Indicative, itemised estimate of what one average lot here could face, built only from this scheme's public-record signals. Indicative ranges, not this building's actual figures, and not financial advice.
Elevated- $23,000
Serious building-defect rectification
Indicative per-lot serious-defect rectification levies (NSW Serious Defects in Residential Apartments research report, 2021; strata special-levy reporting). Scaled for: 1 matter.
- $3,700
Tribunal and legal costs
Indicative per-lot share of tribunal and legal costs in a strata dispute (NCAT). Scaled for: 2 matters.
Litigation · 2 matters
The Owners - Strata Plan No 95242 v Karimbla Properties (No 42) Pty Ltd (No 2) [2025] NSWSC 148
Costs and procedure NSWSC 5 March 2025
COSTS – costs assessment – procedure – where plaintiff to pay defendants’ costs thrown away
The Owners - Strata Plan No 95242 v Karimbla Properties (No 42) Pty Ltd [2024] NSWSC 1625
Building defects NSWSC 12 December 2024
CIVIL PROCEDURE – where plaintiff has served expert evidence – where that expert evidence based upon inspection of some but not all units allegedly affected by defects – where plaintiff belatedly seeks leave to adduce expert evidence in respect of defects alleged to exist in remaining units
Decisions naming this scheme, from NSW Caselaw (NCAT and the courts). The quoted line beneath each is the decision's own catchwords; the topic tag is our grouping of those words. Whether a matter helped or hurt the scheme is not assessed here.
Statutory-warranty outlook
- Structural cover
- Likely expired · est. expiry 23 May 2023
- Non-structural cover
- Ran to 23 May 2019
NSW Home Building Act periods: 6 years for major or structural defects, 2 years for all others. Estimated from the registration date, not the completion date or building contract, so treat the dates as indicative.
Evidence ledger
Registry-backed record: matched to a scheme on the register by its plan number.
| Checked | Found | Match | Last checked |
|---|---|---|---|
| Registry and parcel | NSW Strata Hub, with geometry | Direct | Awaiting first run |
| Governance: AGM, managing agent, annual reporting | Not yet checked | Not matched | Not harvested here yet |
| Litigation: NCAT and courts | 2 matters | Direct | 28 June 2026 |
| Levies and financials | Not yet checked | Not matched | Not in the public record |
| Defects and building-work orders | Checked, none found | Direct | 28 June 2026 |
| Fund balances, current levies, minutes, defects not yet litigated | Not on the public record | Not matched | Never in the public record |
What was checked, what it found, how strong the match, and when each source last ran. A source that has not run here yet reads as not checked, never as checked and clear.